P.L.R Drywall

Drywall Boarding in Newcastle

Before we hang a single sheet on a Newcastle job, the framing, rough-ins, insulation and vapour barrier need to be finished.

Two installers on scaffold fastening drywall on a tall gable wall

Plumbing, wiring and ducts roughed in first

On a Newcastle site, plumbing, electrical and ductwork rough-ins come before board. So does the framing. On new construction, that usually means the house is closed in. Once those trades have finished, the house is ready for the next step.

Cavity insulation and vapour barrier before board

Insulation and vapour barrier also go in before we arrive. In basements the order is the same: framing, rough-ins, insulation and vapour barrier, then board. When every item is done, we start overhead and work down to the walls.

What drywall boarding covers →

Newcastle is part of

Drywall Boarding in other areas

Drywall Boarding in Newcastle: questions

Why do long sheets matter on tall walls and high ceilings?

On high walls and ceilings, joints are harder to reach and show more under light. Long sheets and careful layout keep the number of joints down where they are hardest to deal with.

How do you lay out the sheets on a wall?

Sheets are laid out to keep joints few. Butt joints are staggered rather than lined up. Fewer and better-placed joints make taping easier for whoever finishes the walls afterward.

What changes when boarding a fire-rated wall?

Fire-rated board, often called Type X, is commonly 5/8 inch thick. The rating belongs to the whole assembly, so the board is hung exactly as the drawings and the listed assembly specify.

How are bulkheads and soffits boarded?

Bulkheads and soffits are framed boxes that hide ducts, pipes or beams, or drop a ceiling. The board is cut to fit each face of the box and fastened to its framing.

Book an on-site quote

Calling is fastest:

(365) 499-0040

Or send the form with the rooms, ceiling heights and timing. Quotes are given on site, so we will arrange a visit.

We install the drywall only. The board is supplied by others, and taping and finishing are done by others.

Phone or email, at least one.